Based on the GEMS Implementation Plan,
outlined in section 6.5.2, the major milestones of the GEMS project
occur approximately annually as as follows.. Chapter 8 provides
detailed quarterly milestones
for each Work Package and Task in the first 18 months
|
Month 12
|
Complete the scientific and technical build and validation of 3
separate assimilation systems for Greenhouse gases, Reactive gases,
Aerosol. Complete acquisition of available data.
Complete necessary functionality of
web-site.
|
|
Month 24
|
Complete production and largely complete scientific scientific
assessment of three different reanalyses for Greenhouse gases,
Reactive gases, Aerosol. Make the validated
reanalyses accessible to the
outside world. Distribute feedback to data
providers
|
|
Month 30
|
Complete the technical merge of the 3 assimilation systems into
a unified system. Complete the scientific upgrade of the models and
algorithms based on experiences of trial reanalyses
|
|
Month 42
|
Complete production of the unified reanalyses for Greenhouse
gases, Reactive gases, Aerosol. Complete the build of the
operational system, with operational interfaces to partners
|
|
Month 48
|
Complete the pre-operational trials. Complete
the documentation and the scientific papers.
|
|